Intended Use Plan for the NYS Drinking Water State Revolving Fund

Appendix I

Return to  
Appendix I  

II. Project Multi-Year List
II.A. Project Multi-Year List Additions

ProjectCountySystem Name/
Borrower
DescriptionProject
Cost
ScoreComments
17146SteubenADDISON VILLAGE / Addison (V)Phase 2 of DWSRF #15903., New Ground Water Source$425,9932,150New project with engineering report received after draft IUP printing.
17157GreeneGREENVILLE WATER DISTRICT NO 1 / Greenville (T)Phase 2 of 16688, Upgrade Ground Water Source, Upgrade Distribution System, Extend Distribution System, New System Consolidation$101,7002,115New project with engineering report received after draft IUP printing.
17150SchoharieRICHMONDVILLE VILLAGE / Richmondville (V)Phase 2 of Project #15238, Upgrade Distribution System$381,9402,085New project with engineering report received after draft IUP printing.
17202JeffersonBELLVILLE WD#2 / Ellisburg (T)Consolidation of Belleville-Henderson Central School which has E-coli and Nitrate MCL violations., Extend Distribution System, New System Consolidation$4,214,041230New project with engineering report received after draft IUP printing.
17175ColumbiaTOWN OF CLAVERACK WD #1 / Claverack (T)New system to serve users previously on (C) Hudson raw water main, New Surface Water Treatment Rule Compliance Facility, New Complete System (New System), New Inter-Connection, New System Consolidation$6,563,266185New preapplication received after draft IUP printing.
17195EssexKEENE VALLEY WD / Keene (T)New Ground Water Source, New Storage, Upgrade Distribution System$3,457,603175New preapplication received after draft IUP printing.
17201JeffersonVILLAGE OF ELLISBURG / Ellisburg (V)Extend system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past total coliform detection. , Extend Distribution System, New System Consolidation$3,381,751140New project with engineering report received after draft IUP printing.
17192CattaraugusCENTRAL WATER DISTRICT / Perrysburg (T)Upgrade Water Treatment Plant, Upgrade Ground Water Source, New Transmission, Extend Distribution System$2,700,700135New project with engineering report received after draft IUP printing.
17164EssexTICONDEROGA WD / Ticonderoga (T)Extention of Town system to serve International Paper Mill, Shore Airport Road and the Claymore residential development., New Distribution System, New System Consolidation$6,334,117130New project with engineering report received after draft IUP printing.
17178HerkimerMOHAWK VILLAGE / Mohawk (T)New Storage, Extend Distribution System, Upgrade Distribution System, New System Consolidation$3,279,870130New preapplication received after draft IUP printing.
17169ErieERIE COUNTY WATER AUTHORITY / Erie County Water AuthorityConsolidation of the (C) Buffalo's system into ECWA,, New System Consolidation$172,325,000125New preapplication received after draft IUP prinitng.
17144ChemungTOWN OF CHEMUNG WATER SYSTEM / Chemung (T)New Complete System (New System)$5,773,170125New preapplication received after draft IUP printing.
17207PutnamLAKE PEEKSKILL WD / Putnam Valley (T)Phase 2 of project 16159, New Surface Water Treatment Rule Compliance Facility, Upgrade Distribution System$22,600,250120New preapplication received after draft IUP printing.
17210SullivanWURTSBORO HILLS WATER CO / Mamakating (T)New Ground Water Source, Upgrade Storage, New Distribution System$9,730,204120New project with engineering report received after draft IUP printing.
17151ErieAURORA WATER DISTRICT 18 / Aurora (T)Extend system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past total coliform detection. WD 18, Section B., Extend Distribution System$7,739,935115New project with engineering report received after draft IUP printing.
17171NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFAHillview Reservoir Chambers, Reconstruction-Phase 1-Chamber Roof Replacement, equipment upgrade, Interim chemical system improvement,Safety and Security Improvements (C519A,C519B), Upgrade Storage$12,430,000110New project with engineering report received after draft IUP printing.
17172NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFAHillview Reservoir Chambers Reconstruction-Phase 2 (Phase 1-17171)-Chamber Roof Replacement, equipment upgrade, Interim chemical system improvement,Safety and Security Improvements (C519A,C519B), New Storage$11,300,000110New preapplication received after draft IUP printing.
17173NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFAHillview Reservoir Chambers Reconstruction-Phase 3 (Phases 1-17171, 2-17172), General Chamber Improvements, Flow Control & New Chemical Facilities(C519C), Upgrade Surface Water Treatment Rule Compliance Facility$106,220,000110New preapplication received after draft IUP printing.
17174NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFAHillview Reservoir Chambers Reconstruction-Phase 4 (Phases 1-17171, 2-17172 & 3-17173), Supervisory Controls and Data Acquisition (SCADA) (519D/Westchester), New Storage$5,650,000110New preapplication received after draft IUP printing.
17163EssexTICONDEROGA WD / Ticonderoga (T)New Transmission, New Storage$8,883,467105New preapplication received after draft IUP printing.
17180ErieBUFFALO WATER AUTHORITY / Buffalo City Water BoardUpgrade Water Treatment Plant$8,147,300100New project with engineering report received after draft IUP printing.
17179ClintonSOUTH PLATTSBURGH WATER DISTRICT / Plattsburgh (T)New Pump Station, New Distribution System, New System Consolidation$6,186,750100New preapplication received after darft IUP printing.
17188AlleganyBELFAST WATER DISTRICT / Belfast (T)Upgrade Water Treatment Plant, New Ground Water Source$932,25090New project with engineering report received after draft IUP printing.
17181OswegoROUTE 11 NORTH/FULLER RD. WD / Hastings (T)New Storage, New Distribution System, New System Consolidation$10,253,95985New preapplication received after draft IUP printing.
17152WestchesterPEEKSKILL CITY / Peekskill (C)New Water Treatment to correct organic exceedances., New Water Treatment Plant$25,142,50080New project with engineering report received after draft IUP printing.
17145OneidaTIBBITS/SNOWDEN HILL WD / New Hartford (T)New system to serve area with private contaminated wells. , New Complete System (New System)$2,712,00080New project with engineering report received after draft IUP printing.
17148ClintonROUTR 9/SPELLMAN ROAD / Beekmantown (T)New Distribution System, New System Consolidation$1,795,57080New preapplication received after draft IUP printing.
17186SteubenREXVILLE WATER DISTRICT / West Union (T)New system to serve area with private contaminated wells. , New Complete System (New System)$113,00080New project with engineering report received after draft IUP printing.
17153MonroeROCHESTER CITY / Rochester (C)2004 Watermain Extensions and Improvements., Upgrade Distribution System$1,377,47075New preapplication received after draft IUP printing.
17154MonroeROCHESTER CITY / Rochester (C)2005 Watermain Extensions and Improvements., Upgrade Distribution System$1,401,20075New preapplication received after draft IUP printing.
17155MonroeROCHESTER CITY / Rochester (C)2006 Watermain Extensions and Improvements., Upgrade Distribution System$1,424,93075New preapplication received after draft IUP printing.
17167NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFACity Tunnel 3, Stage 2, Shaft 15B East-Phase 1, Brooklyn-Queens (C545G), New Pump Station$2,666,80060New project with engineering report received after draft IUP printing.
17170NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFACity Tunnel 3, Stage 2, Shaft 15B East- Phase 2 (Phase 1-17167)/Brooklyn-Queens (C545G), New Pump Station$2,666,80060New preapplication received after draft IUP printing.
17176NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFACity Tunnel 3, Stage 2, Shaft 15B East- Phase3 (Phases: 1-17167 & 2-17170),Brooklyn-Queens (C545G), New Pump Station$1,333,40060New preapplication received after draft IUP printing.
17203NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFACity Tunnel 3, Stage 1, Shafts 8B and 15B, Phase 1 - Completion of Chlorination Booster Stations, Upgrade Distribution System$1,130,00060New project with engineering report received after draft IUP printing.
17204NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFACity Tunnel 3, Stage 1, Shafts 8B and 15B, Phase 2 - Completion of Chlorination Booster Stations (pase 1=17203), $1,130,00060New preapplication received after draft IUP printing.
17183SenecaSENECA FALLS VILLAGE / Seneca Falls (V)Upgrade Water Treatment Plant, Upgrade Pump Station$3,260,05060New preapplication received after draft IUP printing.
17182LivingstonTOWN OF MOUNT MORRIS / Mount Morris (T)Route 408 into Tuscarora., Extend Distribution System$6,582,02960New preapplication received after draft IUP printing.
17189JeffersonWATER DISTRICT #5 / Cape Vincent (T)New system to serve area with private contaminated wells. , New Distribution System$1,226,27660New preapplication received after draft IUP printing.
17149RensselaerPETERSBURG WATER DISTRICT / Petersburgh (T)Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Distribution System$951,48850New preapplication received after draft IUP printing.
17191YatesPENN YAN VILLAGE / Penn Yan (V)Upgrade Water Treatment Plant$1,046,34650New project with engineering report received after draft IUP printing.
17190CortlandCINCINNATUS WATER DISTRICT / Cincinnatus (T)Upgrade Ground Water Source, Upgrade Transmission$142,94545New preapplication received after draft IUP printing.
17185JeffersonWATERTOWN TOWN WD 2 / Watertown (T)New Distribution System$1,622,52745New preapplication received after draft IUP printing.
17166NiagaraNEWFANE WD NO1,2,3 CONSOL / Newfane (T)Upgrade Distribution System$2,812,79640New preapplication received after draft IUP printing.
17193EssexAUSABLE FORKS WD / Jay (T)New Storage$1,224,53940New preapplication received after draft IUP printing.
17187OswegoOSWEGO CITY / Oswego (C)Upgrade Distribution System$829,83530New preapplication received after draft IUP printing.
17184FranklinBURKE V / Village of BurkeNew Other Expenses, New Other (OT)$282,50030New preapplication received after draft IUP printing.
17159OrangeKNOLLS WATER CO., INC. / Knolls Water CompanyNew Ground Water Source, Upgrade Storage, New Pump Station$282,50025New preapplication received after draft IUP printing.
17162WestchesterLARCHMONT VILLAGE / Larchmont (V)Replacement of two water storage tanks at 250,000 gallons each/ Byron Place, Upgrade Storage$757,10015New preapplication received after draft IUP printing.
17198NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFATest Borings for City Tunnel 3 and Upstate Tunnel Sites, Phase 1 (C554), NYC & Westchester, Upgrade Transmission$3,862,76715New preapplication received after draft IUP printing.
17199NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFATest Borings for City Tunnel 3 and Upstate Tunnel Sites, Phase 2 (C554), NYC & Westchester, Upgrade Transmission$3,862,76715New preapplication received after draft IUP printing.
17200NY CityNEW YORK CITY-CATSKILL/DELAWARE SYSTEM / NYCMWFATest Borings for City Tunnel 3 and Upstate Tunnel Sites, Phase3 (C554), NYC & Westchester, Upgrade Transmission$3,862,76715New preapplication received after draft IUP printing.
17160WestchesterLARCHMONT VILLAGE / Larchmont (V)Upgrade Distribution System$272,33010New preapplication received after draft IUP printing.
Total # Projects = 53Total Cost = $494,788,499