Project County System Name/
Borrower
Description Project
Cost
Score Comments
16750 Orange KIRYAS JOEL VILLAGE / Kiryas Joel (V) Phase 2 of project 16752., New Water Treatment Plant $1,972,314 2,090 Revised preapplication received. Anticipated closing of the short term loan did not occur during the previous funding cycle. Revised cost and description based on new information. Score revised from 1090 to 2090 to reflect that the project is phase 2 of project 16752.
15848 Essex MORIAH WD / Moriah (T) New Surface Water Treatment Rule Compliance Facility, New Transmission, New Storage $1,918,975 1,240 Revised cost based on new information.
15844 Essex KEENE WD / Keene (T) New Ground Water Source, New Transmission, New Storage, Upgrade Distribution System $1,210,942 1,200 Revised cost based on new information.
17053 Essex UPPER JAY WD / Jay (T) New Surface Water Treatment Rule Compliance Facility, Upgrade Transmission, Upgrade Storage, Upgrade Distribution System $1,906,561 1,185 Revised cost based on new information.
15525 Albany WESTERLO COMMUNITY WATER DISTRICT / Westerlo (T) New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past E. Coli detection. , New Complete System (New System), System Consolidation $443,415 1,185 Revised cost based on new information.
16696 Ulster PINE HILL WATER COMPANY / Shandaken (T) Upgrade Water Treatment Plant, Upgrade Ground Water Source, Upgrade Storage, Upgrade Distribution System $1,846,849 1,175 Revised cost based on new information.
17040 Cattaraugus VERSAILLES WATER DISTRICT / Perrysburg (T) New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past E. Coli detection. , New Complete System (New System) $0 1,175 Project dollar amount adjusted in Final IUP to relect Short Term Loan Closing.
17201 Jefferson VILLAGE OF ELLISBURG / Ellisburg (V) Extend system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past total coliform detection. , Extend Distribution System, New System Consolidation $0 1,135 Revised cost and score based on short term loan closing.
15727 Ontario HONEOYE CONSOLIDATED WD / Richmond (T) Extend system to serve area with private contaminated wells. , Extend Distribution System, Inter-Connection $1,270,274 1,115 Revised cost and score based on short term loan closing and new information.
15284 Saratoga MECHANICVILLE CITY / Mechanicville (C) New Water Treatment Plant $0 1,090 Revised cost and score based on short term loan closing.
17321 Jefferson WESTCOTTS WATER DISTRICT / Hounsfield (T) WD#3 to serve along NYS Route 3. Consolidation of PWS systems addressing SWTR & E-Coli violations., New Distribution System, New System Consolidation $3,223,900 260 Project description revised to include more detail.
17108 Oneida VILLAGE OF BRIDGEWATER / Bridgewater (V) New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System), New System Consolidation $3,871,727 240 Revised score from 100 to 240 based on new information.
17050 Oswego SANDY CREEK/LACONA JOINT WATERWORKS / Sandy Creek/Lacona (V) Address inadequate source capacity & system pressure, E-Coli violation., Upgrade Ground Water Source, Upgrade Distribution System $3,019,000 225 Revised cost based on new information.
15839 Essex LEWIS WD / Lewis (T) New Ground Water Source, Upgrade Distribution System $1,330,013 215 Revised cost based on new information.
16744 Delaware FLEISCHMANNS VILLAGE / Fleischmanns (V) New Ground Water Source, New Storage, Upgrade Distribution System $3,000,000 205 Revised score from 105 to 205 based on new information. Revised cost based on new information.
17195 Essex KEENE VALLEY WD / Keene (T) New Ground Water Source, New Storage, Upgrade Distribution System $4,701,374 165 Revised cost based on new information.
17225 Oneida HAMLET OF VIENNA WD / Vienna (T) New Surface Water Treatment Rule Compliance Facility, New Water District $4,048,000 160 Revised cost based on new information. Revised score from 60 to 160 based on new information.
17357 Rensselaer SCHODACK WATER DISTRICT #5/PONDVIEW / Schodack (T) Serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past total coliform detection., New Storage, Extend Distribution System, New System Consolidation $2,231,410 150 Revised score from 115 to 150 based on new information
17060 Jefferson TOWN OF CAPE VINCENT WD #4 / Cape Vincent (T) New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past total coliform detection. , Extend Distribution System, New System Consolidation, New Water District $7,329,068 145 Revised cost based on new information.
17105 St.Lawrence HAMLET OF HELENA / Brasher (T) New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System) $1,447,000 140 Revised cost based on new information.
16911 Tioga TOWN OF BARTON WATER DISTRICT / Barton (T) Extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supplies with past coliform detections., Extend Distribution System $1,123,400 140 Revised cost based on new information.
17372 Oswego (T) MEXICO WD#2 / Mexico (T) New Ground Water Source, New Storage, New Distribution System $9,675,000 135 Revised score from 125 to 135 based on new information.
16496 Ulster NAPANOCH WATER DISTRICT / Wawarsing (T) New Ground Water Source, New Transmission $2,964,000 135 Revised score from 95 to 135 based on new information.
16635 Lewis COPENHAGEN VILLAGE / Copenhagen (V) New Ground Water Source, Upgrade Distribution System $2,509,731 130 Revised score from 105 to 130 based on new information.
16298 Rockland NYACK VILLAGE WATER SUPPLY / Nyack (V) New Transmission $1,105,105 110 Revised score from 60 to 110 points based on new information.
15829 Essex MINERVA WD / Minerva (T) New Ground Water Source, Upgrade Distribution System, New System Consolidation $1,438,869 105 Revised cost based on new information.
17104 Saratoga CLIFTON PARK WATER AUTHORITY / Clifton Park (T) East Side Drive WD connection to CPWA, to serve private contaminated wells, consolidation of public water supplies, Extend Distribution System $1,329,730 105 Revised cost based on new information. Revised score from 45 to 105 based on new information.
16807 Franklin TUPPER LAKE (T) WD #17, LITTLE WOLF WD / Tupper Lake (T) New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System) $540,000 85 Project Borrower changed its name from the Town of Altamont to the Town of Tupper Lake. Revised hardship status based on new information.
17077 Rensselaer NORTH GREENBUSH WD #13 / North Greenbush (T) New system to serve area with private contaminated wells (Snyder's Lake Area). , New System Consolidation, New Water District $4,583,100 80 Revised cost based on new information.
15072 Orange BEAVER DAM LAKE WATER CORP. / Beaver Dam Lake Corp. New Storage, Upgrade Distribution System $766,700 60 Revised cost based on new information.
Total # Projects: 30