Final Intended Use Plan for the New York State Drinking Water State Revolving Fund

I. Project Readiness List

I. A. Project Readiness List Additions

Project County System Name/
Borrower
Description Project
Cost
Score Comments
17470 Herkimer HERKIMER VILLAGE / Herkimer (V) Phase 2 of 16676, New Surface Water Treatment Rule Compliance Facility $200,000 2,130 New project with engineering report received after draft IUP printing.
17471 Dutchess POUGHKEEPSIE CITY/TOWN TREATMENT PLANT / P'keepsie(C)(T)/Wap.Falls (V) Phase 4 of DWSRF 15654, valve replacement program, unidirectional flushing to permit chlorimine system to go on-line, Upgrade Distribution System $1,894,988 2,100 New project with engineering report received after draft IUP printing.
17473 Jefferson LAFAVE ROAD WATER DISTRICT / Le Ray (T) Consolidation of existing public water systems with GUDI wells, coliform and lead violations., New Distribution System, New System Consolidation $6,388,443 280 New project with engineering report received after draft IUP printing.
17456 Hamilton INDIAN LAKE WD / Indian Lake (T) New Surface Water Treatment Rule Compliance Facility, Upgrade Water Treatment Plant, New Ground Water Source, Upgrade Distribution System $2,282,000 255 New project with engineering report received after IUP printing.
17273 Oswego TOWN OF MEXICO AREA #1 / Mexico (T) New Ground Water Source, New Storage, New Distribution System $8,480,000 190 Previously withdrawn project has been reactivated by applicant.
17382 Allegany HOUGHTON WATER DISTRICT / Caneadea (T) Upgrade Water Treatment Plant, New Ground Water Source, New Transmission, Upgrade Distribution System $6,535,600 175 Engineering report received, project now ready. Previously only on multi-year list. Revised cost based on new information.
17392 Warren PIONEER VILLAGE / Pioneer Village Imp. Assoc. Serve private contaminated wells., New Surface Water Treatment Rule Compliance Facility, New Inter-Connection, New System Consolidation $208,575 175 Project previously withdrawn by applicant. Applicant now requests project be reactivated.
17461 Orange PHEASANT HILL / Pheasant Hill Water Corp Rehabilitation of water system to address coliform contamination, Upgrade Water Treatment Plant, New Ground Water Source, New Storage $2,938,700 165 New project with engineering report received after draft IUP printing.
15947 Tompkins LANSING (T) WD #17, EXT. 5 / Lansing (T) Town of Lansing, Tompkins Co.District No. 17, Extension No. 5., Extend Distribution System $850,000 165 Engineering report received, project now ready. Previously on multiyear list only. Revised score from 65 points to 165 points and revised project cost based on now information.
17454 St.Lawrence EAST LOUISVILLE WD#3 / Louisville (T) Consolidation of water systems with past coliform detections., New Storage, New Distribution System, New System Consolidation $5,263,600 150 New project with engineering report received after draft IUP printing.
17455 Franklin WATER DISTRICT #3 / Malone (T) New Distribution System, New System Consolidation $1,891,000 145 New project with engineering report received after draft IUP printing.
16911 Tioga TOWN OF BARTON WATER DISTRICT / Barton (T) Extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supplies with past coliform detections., Extend Distribution System $984,400 140 Engineering report received, project now ready. Previously only on multi-year list. Hardship project.
17480 Onondaga SMOKEY HOLLOW WD / LaFayette (T) Connection with OCWA for GUDI source compliance., Upgrade Distribution System, New Inter-Connection $1,441,900 110 New project with engineering report received after draft IUP printing.
17488 Westchester WESTCHESTER JOINT WATER WORKS / (T)amp;(V)'sHarrison&Mamaroneck   $43,300,000 105 New project with engineering report received after draft IUP printing
17438 Oneida ROME CITY / Rome (C) Filter and storage tank rehabilitation., Upgrade Water Treatment Plant, Upgrade Storage $2,750,000 105 Engineering report received, project now ready. Previously only on multi-year list. Revised cost based on new information.
17416 Erie TOWN OF NEWSTEAD WD#10 / Newstead (T)   $1,400,000 105 Engineering report received, project now ready. Previously only on multi-year list. Revised cost based on new information.
15787 Chautauqua CLYMER WATER DISTRICT / Clymer (T) New Ground Water Source $300,000 100 Engineering report received, project now ready. Previously only on multi-year list. Revised cost based on new information. Revised score from 95 to 100 based on new information.
17332 Cattaraugus PROSPECT STREET WATER DISTRICT / Perrysburg (T) Extend Distribution System, Upgrade Distribution System, System Consolidation $309,000 90 Engineering report received, project now ready. Previously only on multi-year list.
17448 Washington KINGSBURY WD (QUEENSBURY) / Kingsbury (T) New water district to serve residents in area of groundwater contamination , New Distribution System, New Water District $845,000 85 Engineering report received, project now ready. Perviously only on multi-year list. Revised score from 60 to 85 points based on new information.
16139 St.Lawrence MASSENA VILLAGE / Massena (V) Upgrade Water Treatment Plant $2,945,000 80 Revised cost based on new information.
15344 Jefferson TOWN OF LYME WATER DIST. NO. 2 / Lyme (T) New Complete System (New System), New Distribution System $2,388,662 80 Project previously on multi-year list only, project now ready.
17478 Clinton ROUTE 11 WD / Champlain (T) Extend Distribution System $1,267,380 55 New project with engineering report received after draft IUP printing.
17479 Clinton WEST SERVICE ROAD WD / Champlain (T) Extend Distribution System $675,284 55 New project with engineering report received after draft IUP printing.
17475 Jefferson WD#1 (RTE. 37) / Theresa (T) New Distribution System $277,160 55 New project with engineering report received after draft IUP printing.
17458 Onondaga METROPOLITAN WATER BOARD / Metropolitan Water Board Western Reservoir storage, Upgrade Storage $10,800,000 40 New project with engineering report received after draft IUP printing.
17459 Onondaga METROPOLITAN WATER BOARD / Metropolitan Water Board Eastern Reservoir storage, Upgrade Storage $14,300,000 40 New project with engineering report received after draft IUP printing.
17460 Onondaga METROPOLITAN WATER BOARD / Metropolitan Water Board Installing cover for Terminal Reservoir, Upgrade Storage $16,050,000 40 New project with engineering report received after draft IUP printing.
17467 Ulster SAUGERTIES (VILLAGE) WATER DIS / Saugerties (V)   $2,141,400 25 New project with engineering report received after draft IUP printing.
Total # Projects: 28 Total Cost: $139,108,092