Final Intended Use Plan for the New York State Drinking Water State Revolving Fund
I. Project Readiness List
I. A. Project Readiness List Additions
| Project | County | System Name/ Borrower |
Description | Project Cost |
Score | Comments |
|---|---|---|---|---|---|---|
| 17515 | Orange | NEWBURGH CITY / Newburgh (C) | Phase 2 of project 16754 Cost overrun, Upgrade Water Treatment Plant, Upgrade Transmission | $2,077,162 | 2,165 | New project with engineering report received after draft IUP printing. |
| 16010 | Oswego | RICHLAND (T) W.D. NO. 1 / Richland (T) | New (T) Richland Water District #1 and consolidation of Brennan Beach Campground, New Complete System (New System), Extend Distribution System | $0 | 1,215 | Project was anticipated to close during the previous funding cycle and was excluded from the draft IUP. Project did not close. |
| 15680 | Erie | COLDEN (T) WATER DISTRICT #1 / Colden (T) | Extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supply with past coliform detections., Extend Distribution System | $1,000,000 | 1,120 | Project was anticipated to close during the previous funding cycle and was excluded from the draft IUP. Project did not close. |
| 17544 | Oneida | TOWN/VILLAGE WATER SYSTEM / Vernon (T)&(V) | New Surface Water Treatment Rule Compliance Facility, Upgrade Transmission, New Storage, Upgrade Pump Station, New Distribution System, New System Consolidation | $10,003,000 | 230 | New project with engineering report received after draft IUP printing. |
| 17550 | Tompkins | GROTON VILLAGE / Groton (V) | New Surface Water Treatment Rule Compliance Facility | $323,719 | 210 | New project with engineering report received after draft IUP printing. |
| 16261 | Oswego | TOAD HARBOR/CONSTANTIA WD / Constantia (T) | New Surface Water Treatment Rule Compliance Facility, New Storage, New Pump Station, New Distribution System, New Inter-Connection, New System Consolidation | $13,560,500 | 200 | Revised score from 55 points to 200 points based on new information. Engineering report received, project now ready. Previously only on multi-year list only. Revised cost based on new information. |
| 17538 | Oswego | WATER DISTRICT #2 / Richland (T) | New Surface Water Treatment Rule Compliance Facility, New Ground Water Source, New Tranmission, New Storage, New Distribution System | $9,560,000 | 200 | New project with engineering report received after draft IUP printing. |
| 16511 | Genesee | GENESSE COUNTY WATER SUPPLY / Monroe Co. Water Authority | New system to serve area with private contaminated wells, consolidate public water supply. , New Transmission, New System Consolidation | $20,010,000 | 190 | Revised score from 95 points to 190 points based on new information. Revised cost bsed on new information. Engineering report received project previously on muli-year list only, project now ready. |
| 17306 | Jefferson | WATER DISTRICT #2 / Henderson (T) | New Surface Water Treatment Rule Compliance Facility, New Distribution System, New System Consolidation | $3,848,615 | 180 | Revised score from 55 points to 180 points based on new information. Engineering report received, project now ready. Previously only on multi-year list. Revised cost based on new information. |
| 16510 | Schenectady | DELANSON VILLAGE WATER WORKS / Delanson (V) | Improve inadequate system pressure, upgrade mains, extension to connect existing homes and school, replacement of Upper resevoir raw water transmission main, new intake., New Transmission, Extend Distribution System, Upgrade Distribution System | $2,935,500 | 175 | Engineering Report received, project now ready. Previously only on multi-year list only. Revised score from 110 to 175 based new information. Revised cost based on new information. |
| 17425 | Chenango | SO. NEW BERLIN WATER DISTRICT / New Berlin (T) | New Ground Water Source, New Tranmission, New Storage, Upgrade Distribution System | $2,163,000 | 175 | Engineering report received, project now ready. Previously on multi-year list only. Revised score from 85 to 175 and revised cost based on new information. |
| 17522 | Ontario | NAPLES VILLAGE / Naples (V) | Address GWUDI spring sources., New Surface Water Treatment Rule Compliance Facility, Upgrade Ground Water Source, Upgrade Distribution System | $1,746,869 | 165 | New project with engineering report received after draft IUP printing. |
| 17537 | Delaware | DOWNSVILLE WATER DISTRICT / Colchester (T) | Package Filtration Plant for GWUDI Spring Source and Addition of Corrosion Control Treatment., New Surface Water Treatment Rule Compliance Facility, New Water Treatment Plant | $92,400 | 165 | New project with engineering report received after draft IUP printing. |
| 17225 | Oneida | HAMLET OF VIENNA WD / Vienna (T) | New Surface Water Treatment Rule Compliance Facility, New Water District | $4,500,000 | 160 | Project was anticipated to close during the previous funding cycle and was excluded from the draft IUP. Project did not close. |
| 17181 | Oswego | ROUTE 11 NORTH/FULLER RD. WD / Hastings (T) | Consolidate public water supplies with past coliform and pressure violations, New Storage, New Distribution System, New System Consolidation | $9,403,900 | 155 | Project was anticipated to close during the previous funding cycle and was excluded from the draft IUP. Project did not close. |
| 17339 | Erie | S. EAST ERIE CO. REGIONAL WATER PROJECT / Aurora (T) | Aurora WD19, Wales WD's2&3. Extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supply with past coliform detections, Storage, Pump Station, Extend Distribution System, System Consolidation | $6,400,000 | 150 | Engineering Report received, project now ready. Previously only on mulit-year list only. Revised cost based on new information. |
| 17514 | Cattaraugus | DELEVAN VILLAGE / Delevan (V) | New Surface Water Treatment Rule Compliance Facility, Upgrade Ground Water Source, Upgrade Storage, Upgrade Distribution System | $1,608,425 | 145 | New project with engineering report received after draft IUP printing. |
| 16496 | Ulster | NAPANOCH WATER DISTRICT / Wawarsing (T) | New Ground Water Source, New Transmission | $7,649,100 | 135 | Project was anticipated to close during the previous funding cycle and was excluded from the draft IUP. Project did not close. |
| 17463 | Westchester | BEDFORD CONSOLIDATED W.D. / Bedford (T) | New Water Treatment Plant | $1,100,000 | 130 | Engineering report received, project now ready. Previously only on multi-year list only. Project divided into two phases (17463 & 17518) |
| 17417 | Delaware | ARKVILLE WATER DISTRICT / Middletown (T) | Extend distribution, 100,000 gallons of storage, 100 gpm well, system consolidation., New Ground Water Source, New Storage, Extend Distribution System, Extend System Consolidation | $3,791,000 | 130 | Revised project score from 115 points to 130 points based on new information. Engineering Report received, project now ready. Previously only on multi-year list only. Revised cost based on new information. |
| 17516 | St.Lawrence | OSWEGATCHIE (T) / Oswegatchie (T) | Joint water system improvement project between (T) Oswegatchie, (T) Lisbon and (V) Huevelton, Upgrade Ground Water Source, Upgrade Storage, Upgrade Distribution System, New Inter-Connection, New System Consolidation | $10,973,000 | 120 | New project with engineering report received after draft IUP printing. |
| 17443 | Albany | ALTAMONT VILLAGE / Altamont (V) | New Brandle Road Wells, Disinfection, and Transmission Main, New Ground Water Source | $1,394,550 | 90 | Revised score from 70 points to 90 points based on new information. Engineering report received, project now ready.Previously on multiyear list only. |
| 17512 | St.Lawrence | NEWTON FALLS WATER DISTRICT / Clifton (T) | New Ground Water Source | $800,000 | 90 | New project with engineering report received after draft IUP printing. |
| 17523 | Orange | MONTGOMERY W.D. #1 / Town of Montgomery | Extend WD #1 to consolidate several water supplies, New System Consolidation | $269,730 | 90 | New project with engineering report received after draft IUP printing. |
| 17510 | Oswego | NORTH AREA WD / Volney (T) | New Distribution System, New System Consolidation | $6,540,000 | 80 | New project with engineering report received after draft IUP printing. |
| 17533 | Clinton | CHAMPLAIN VILLAGE / Champlain (V) | Upgrade Water Treatment Plant, New Storage, Upgrade Distribution System | $1,883,226 | 75 | New project with engineering report received after draft IUP printing. |
| 17300 | Washington | FORT EDWARD WD #4 (ROUTE 4) / Fort Edward (T) | New water district along Hudson River including distribution mains, booster disinfection, new storage tank, new pump station., New Complete System (New System), New Storage | $7,575,000 | 75 | Revised score from 60 points to 75 points based on new information.Engineering Report received, project now ready. Previously only on multi-year list only. Revised cost based on new information. |
| 17526 | Allegany | WELLSVILLE WATER DISTRICT / Wellsville (T) | Extend Distribution System, New Water District | $1,192,450 | 70 | New project with engineering report received after draft IUP printing. |
| 17548 | Albany | MENANDS VILLAGE / Menands (V) | Upgrade Pump Station, Upgrade Distribution System | $5,655,000 | 60 | New project with engineering report received after draft IUP printing. |
| 17547 | Broome | WHITNEY POINT VILLAGE / Whitney Point (V) | New Wells, Main Street Wellfield/Pumphouse Improvements., Upgrade Ground Water Source, New Ground Water Source | $470,000 | 55 | New project with engineering report received after draft IUP printing. |
| 17517 | Niagara | LOCKPORT CITY WTP / Lockport (C) | Replace waterline on Market St. between Union and Spring , Upgrade Distribution System | $640,000 | 30 | New project with engineering report received after draft IUP printing. |
| 17524 | Westchester | NORTH CASTLE WD #2 / Town of New Castle | New well and storage, New Ground Water Source, New Storage | $1,458,695 | 25 | New project with engineering report received after draft IUP printing. |
| 17540 | Genesee | OAKFIELD VILLAGE / Oakfield (V) | Upgrade Transmission, Upgrade Storage, Upgrade Distribution System | $1,147,575 | 25 | New Project with engineering report received after draft IUP printing. |
| 17525 | Westchester | NORTH CASTLE WD #1 / Town of North Castle | Rehabilitation of water storage tanks, Upgrade Storage | $813,500 | 15 | New project with engineering report received after draft IUP printing. |
| 17527 | Genesee | OAKFIELD VILLAGE / Oakfield (V) | Upgrade Transmission, Upgrade Distribution System | $1,147,575 | 15 | New project with engineering report received after draft IUP printing. |
| 17539 | Rensselaer | CASTLETON VILLAGE PWS / Castleton-on-Hudson (V) | Replacement in-kind of aged water mains., Upgrade Distribution System | $1,661,400 | 10 | New project with engineering report received after draft IUP printing. |