NYS Drinking Water State Revolving Fund
Category C Hardship List for October 1, 2005 to September 30, 2006
Project | County | System Name/ Borrower |
Description | Pop. | Project Cost |
Score | Cumulative Total |
---|---|---|---|---|---|---|---|
17217 | Chautauqua | TOWN OF PORTLAND WATER DISTRICT NO. 5 / PORTLAND (T) | Phase II of DWSRF #16775 - extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supply with past turbidity violations., Extend Distribution System | 183 | $514,400 | H | $514,400 |
17423 | Delaware | ANDES WD / ANDES (T) | Phase 3 of project #15916 Water supply , treatment and distribution improvements., Upgrade Distribution System | 300 | $257,500 | H | $771,900 |
17287 | Erie | FARNHAM VILLAGE / FARNHAM (V) | Phase 2 of DWSRF#16271., Upgrade Transmission, New Storage, Upgrade Distribution System | 404 | $250,000 | H | $1,021,900 |
15848 | Essex | MORIAH WD / MORIAH (T) | New Surface Water Treatment Rule Compliance Facility, New Transmission, New Storage | 3,100 | $1,918,975 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15873 | Essex | WESTPORT WD / WESTPORT (T) | New Ground Water Source, Upgrade Distribution System | 800 | $0 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17085 | Franklin | MALONE V / MALONE (V) | New Surface Water Treatment Rule Compliance Facility, New Storage | 13,000 | $0 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17202 | Jefferson | BELLVILLE WD#2 / ELLISBURG (T) | Consolidation of Belleville-Henderson Central School which has E-coli and Nitrate MCL violations., Extend Distribution System, New System Consolidation | 355 | $0 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15057 | Jefferson | ANTWERP VILLAGE / ANTWERP (V) | Upgrade Water Treatment Plant, Upgrade Ground Water Source, Upgrade Transmission, Upgrade Pump Station | 900 | $0 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16010 | Oswego | RICHLAND (T) W.D. NO. 1 / RICHLAND (T) | New (T) Richland Water District #1 and consolidation of Brennan Beach Campground, New Complete System (New System), Extend Distribution System | 250 | $0 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15773 | Columbia | STOCKPORT WD #2 (CONSOLIDATED) / STOCKPORT (T) | New Surface Water Treatment Rule Compliance Facility, New Transmission, New Storage | 3,100 | $0 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15655 | Sullivan | LIBERTY VILLAGE / LIBERTY (V) | Upgrade Water Treatment Plant, Upgrade Transmission, New Storage, New Pump Station, New System Consolidation | 4,800 | $0 | H | $2,940,875 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15844 | Essex | KEENE WD / KEENE (T) | New Ground Water Source, New Transmission, New Storage, Upgrade Distribution System | 300 | $1,210,942 | H | $4,151,817 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16278 | Hamilton | LONG LAKE WD / LONG LAKE (T) | New Ground Water Source, New Storage, Upgrade Distribution System | 800 | $0 | H | $4,151,817 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16979 | Chemung | VILLAGE OF VAN ETTEN / VAN ETTEN (V) | New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past E. Coli detection. , New Complete System (New System) | 560 | $0 | H | $4,151,817 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17103 | Jefferson | MANNSVILLE VILLAGE / MANNSVILLE (V) | New Surface Water Treatment Rule Compliance Facility, New Storage, New Distribution System | 500 | $500,000 | H | $4,651,817 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15701 | Greene | ATHENS VILLAGE / ATHENS (V) | Upgrade Water Treatment Plant | 1,850 | $900,000 | H | $5,551,817 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16431 | Oneida | REMSEN VILLAGE / REMSEN (V) | New Surface Water Treatment Rule Compliance Facility | 650 | $0 | H | $5,551,817 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17053 | Essex | UPPER JAY WD / JAY (T) | New Surface Water Treatment Rule Compliance Facility, Upgrade Transmission, Upgrade Storage, Upgrade Distribution System | 234 | $1,906,561 | H | $7,458,378 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17069 | Essex | WILLSBORO WD / WILLSBORO (T) | Extend to serve Willsboro Bay WD for SWTR compliance., Upgrade Distribution System, New System Consolidation | 1,571 | $0 | H | $7,458,378 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15525 | Albany | WESTERLO COMMUNITY WATER DISTRICT / WESTERLO (T) | New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past E. Coli detection. , New Complete System (New System), System Consolidation | 280 | $443,415 | H | $7,901,793 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16730 | Steuben | PULTENEY WATER SUPPLY SYSTEM / PULTENEY (T) | New system to serve private contaminated wells, consolidate public water supplies, eliminate public water supplies with surface water treatment rule violations., New Complete System (New System) | 235 | $0 | H | $7,901,793 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15237 | Chenango | SHERBURNE VILLAGE / SHERBURNE (V) | New Ground Water Source, New Transmission, Upgrade Storage, Upgrade Distribution System | 1,531 | $1,483,000 | H | $9,384,793 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15085 | Saratoga | SCHUYLERVILLE-VICTORY JWC / SCHUYLERVILLE (V) | New Surface Water Treatment Rule Compliance Facility, New Ground Water Source, Upgrade Distribution System | 1,900 | $0 | H | $9,384,793 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17175 | Columbia | TOWN OF CLAVERACK WD #1 / CLAVERACK (T) | New system to serve users previously on (C) Hudson raw water main, New Surface Water Treatment Rule Compliance Facility, New Complete System (New System), New Inter-Connection, New System Consolidation | 1,200 | $227,000 | H | $9,611,793 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17029 | Washington | VILLAGE OF SALEM WATER SYSTEM / SALEM (V) | New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past E. Coli detection. , New Complete System (New System) | 920 | $0 | H | $9,611,793 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16696 | Ulster | PINE HILL WATER COMPANY / SHANDAKEN (T) | Upgrade Water Treatment Plant, Upgrade Ground Water Source, Upgrade Storage, Upgrade Distribution System | 477 | $1,846,849 | H | $11,458,642 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17052 | Essex | WILMINGTON WD / WILMINGTON (T) | Upgrade Transmission, New Storage, Upgrade Distribution System | 980 | $971,526 | H | $12,430,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16748 | Tompkins | NEWFIELD WD / NEWFIELD (T) | Establish Water District No. 2, New Complete System (New System) | 1,100 | $0 | H | $12,430,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16645 | Steuben | URBANA WATER DISTRICT / URBANA (T) | Extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supply with past E. Coli detection., Extend Distribution System | 90 | $1,000,000 | H | $13,430,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17040 | Cattaraugus | VERSAILLES WATER DISTRICT / PERRYSBURG (T) | New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past E. Coli detection. , New Complete System (New System) | 145 | $0 | H | $13,430,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15096 | Schoharie | MIDDLEBURGH VILLAGE / MIDDLEBURGH (V) | Upgrade Ground Water Source, Upgrade Storage, Upgrade Distribution System | 1,398 | $0 | H | $13,430,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16716 | Jefferson | GLEN PARK UPPER UTILITIES (V) / GLEN PARK (V) | New system to serve area with private contaminated wells. , New Storage, Extend Distribution System | 50 | $0 | H | $13,430,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17195 | Essex | KEENE VALLEY WD / KEENE (T) | New Ground Water Source, New Storage, Upgrade Distribution System | 450 | $0 | H | $13,430,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16732 | Greene | VILLAGE OF HUNTER / HUNTER (V) | Consolidate public water supply, , New Surface Water Treatment Rule Compliance Facility | 429 | $1,854,000 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15908 | Jefferson | TOWN OF BROWNVILLE WATER DISTRICT NO. 1 / BROWNVILLE (T) | Extend system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past E. Coli detection. , Extend Distribution System, System Consolidation | 150 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16770 | St.Lawrence | WANAKENA WATER COMPANY / WANAKENA WATER COMPANY | Reconstruction of the Hamlet of Wanakena's existing water distribution system to eliminate E. Coli detections. , Upgrade Distribution System | 400 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16910 | Jefferson | PIERREPONT MANOR WATER DISTRICT / ELLISBURG (T) | New system to serve area with private contaminated wells. , New Complete System (New System) | 250 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16259 | Chemung | WELLSBURG VILLAGE / WELLSBURG (V) | New Transmission, New Pump Station, New Inter-Connection | 650 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17105 | St.Lawrence | HAMLET OF HELENA / BRASHER (T) | New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System) | 150 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16146 | Otsego | MILFORD VILLAGE / MILFORD (V) | New Ground Water Source, Upgrade Distribution System | 510 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15055 | Herkimer | LITTLE FALLS CITY / LITTLE FALLS (C) | New Surface Water Treatment Rule Compliance Facility | 5,800 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16530 | Oswego | PULASKI VILLAGE / PULASKI (V) | New Storage, New Pump Station | 2,398 | $0 | H | $15,284,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17188 | Allegany | BELFAST WATER DISTRICT / BELFAST (T) | Upgrade Water Treatment Plant, New Ground Water Source | 750 | $825,000 | H | $16,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17054 | Cayuga | SPRINGPORT WATER DISTRICT NO. 2 / SPRINGPORT (T) | Cayuga Lake Intercommunity Water Board - Towns of Springport and Fleming. Extend to serve private contaminated wells., New Storage, Extend Distribution System, New Inter-Connection | 1,500 | $0 | H | $16,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15680 | Erie | TOWN OF COLDEN WATER DISTRICT #1 / COLDEN (T) | Extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supply with past coliform detections., Extend Distribution System | 450 | $1,000,000 | H | $17,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15574 | Steuben | COHOCTON VILLAGE / COHOCTON (V) | New Ground Water Source | 854 | $0 | H | $17,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15829 | Essex | MINERVA WD / MINERVA (T) | New Ground Water Source, Upgrade Distribution System, New System Consolidation | 800 | $0 | H | $17,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16087 | Erie | TOWN OF NEWSTEAD / NEWSTEAD (T) | New Storage, Extend Distribution System, System Consolidation | 5,000 | $1,000,000 | H | $18,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17099 | Oswego | VOLNEY AIRPORT WATER SYSTEM / VOLNEY (T) | New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System) | 921 | $0 | H | $18,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17088 | Oneida | HIGBY ROAD WATER DISTRICT / NEW HARTFORD (T) | New Storage, New Pump Station, Extend Distribution System | 700 | $0 | H | $18,109,168 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17022 | Jefferson | SACKETS HARBOR VILLAGE / SACKETS HARBOR (V) | Extension to serve area with private contaminated wells. , Extend Distribution System | 1,300 | $629,630 | H | $18,738,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15147 | Schoharie | WARNERVILLE W.D. - (T)RICHMONDVILLE / RICHMONDVILLE (T) | New system to serve area with private contaminated wells, consolidate public water supply. , New Distribution System | 550 | $405,000 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15284 | Saratoga | MECHANICVILLE CITY / MECHANICVILLE (C) | New Water Treatment Plant | 8,000 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16889 | Oneida | KIRKLAND (T) ROUTE 5 WATER DISTRICT / KIRKLAND (T) | New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System) | 300 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15684 | Greene | TOWN OF NEW BALTIMORE NEW SYSTEM / NEW BALTIMORE (T) | Extend system to serve area with private contaminated wells, consolidate public water supply. , Extend Distribution System, New System Consolidation | 1,300 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16057 | Steuben | HORNELL CITY / HORNELL (C) | New Storage, New Pump Station, Upgrade Distribution System | 9,019 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16922 | Herkimer | GRAHM, NEWPORT & BROWN RD WD / SCHUYLER (T) | New system to serve area with private contaminated wells. , New Complete System (New System) | 260 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17059 | Chautauqua | TOWN OF SHERIDAN ROUTE 5 WATERLINE / SHERIDAN (T) | Extend to serve private contaminated wells, consolidate public water supplies., Extend Distribution System | 280 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17056 | Allegany | ANDOVER VILLAGE PUBLIC WATER / ANDOVER (V) | Upgrade Storage, Upgrade Distribution System | 1,130 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
15576 | Steuben | COHOCTON VILLAGE / COHOCTON (V) | Water System Pressure Deficiency Remediation: replace 4" mains & loop dead end connections, install additional valves., Upgrade Distribution System | 854 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
16818 | Chautauqua | HANOVER WATER DISTRICT #1 / HANOVER (T) | New Storage, Upgrade Distribution System | 2,173 | $0 | H | $19,143,798 |
NOTE: Short - Term Loan Closed, Project Cost Shown is Remaining Balance Not Funded With Short Term Loan | |||||||
17321 | Jefferson | WESTCOTTS WATER DISTRICT / HOUNSFIELD (T) | WD#3 to serve along NYS Route 3. Consolidation of PWS systems addressing SWTR & E-Coli violations., New Distribution System, New System Consolidation | 300 | $3,223,900 | H | $22,367,698 |
17281 | Yates | HIMROD/PLUM POINT WATER DISTRICT / MILO (T) | Extend Distribution System, System Consolidation | 750 | $3,838,050 | H | $26,205,748 |
16953 | Lewis | CONSOLIDATED WD#1 (T) LOWVVILLE / LOWVILLE (T) | New Surface Water Treatment Rule Compliance Facility, Upgrade Storage, Extend Distribution System, Upgrade Distribution System, New System Consolidation | 280 | $3,200,000 | H | $29,405,748 |
15881 | Essex | WADHAMS WD / WESTPORT (T) | New Surface Water Treatment Rule Compliance Facility, New Inter-Connection, New System Consolidation | 140 | $2,114,490 | H | $31,520,238 |
17108 | Oneida | VILLAGE OF BRIDGEWATER / BRIDGEWATER (V) | New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System), New System Consolidation | 600 | $3,303,000 | H | $34,823,238 |
17050 | Oswego | SANDY CREEK/LACONA JOINT WATERWORKS / SANDY CREEK/LACONA (V) | Address inadequate source capacity & system pressure, E-Coli violation., Upgrade Ground Water Source, Upgrade Distribution System | 1,435 | $4,775,000 | H | $39,598,238 |
17390 | Franklin | NORTH BANGOR WS / BANGOR (T) | Replace existing GWUDI source with new wells. Provide service for existing homes on contaminated wells., New Ground Water Source, New Storage, New Distribution System | 50 | $2,654,962 | H | $42,253,200 |
17272 | Delaware | TOWN OF DAVENPORT WD / DAVENPORT (T) | Acquisition and improvement of private water company by (T) Davenport. New wells to replace GWUDI springs, New Ground Water Source, New Storage, New Water District | 104 | $823,000 | H | $43,076,200 |
15770 | Schuyler | HECTOR WATER DISTRICT / HECTOR (T) | 928 | $4,880,912 | H | $47,957,112 | |
17354 | Washington | WHITEHALL VILLAGE / WHITEHALL (V) | New Surface Water Treatment Rule Compliance Facility, New Transmission, New Storage, Upgrade Distribution System | 3,600 | $9,997,000 | H | $57,954,112 |
15813 | Hamilton | RAQUETTE LAKE WD / LONG LAKE (T) | New Surface Water Treatment Rule Compliance Facility, New Storage, Upgrade Distribution System | 85 | $717,551 | H | $58,671,663 |
17045 | Jefferson | REDWOOD WATER DISTRICT / ALEXANDRIA (T) | New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System) | 500 | $7,235,436 | H | $65,907,099 |
15980 | Saratoga | TOWN OF MOREAU / MOREAU (T) | Extension to serve properties in WD #6, and consolidate several exisitng public water systems, New Storage, Extend Distribution System, New System Consolidation | 2,100 | $5,400,000 | H | $71,307,099 |
16744 | Delaware | FLEISCHMANNS VILLAGE / FLEISCHMANNS (V) | New Ground Water Source, New Storage, Upgrade Distribution System | 625 | $3,000,000 | H | $74,307,099 |
17333 | Steuben | SPAULDING DR/LAKE SALUBRIA WATER DISTR. / BATH (T) | Consolidation of 18 public water systems, eliminate PWS with organic exceedance., Extend Distribution System, Upgrade Distribution System, System Consolidation | 1,195 | $5,460,087 | H | $79,767,186 |
15540 | Jefferson | THERESA VILLAGE / THERESA (V) | New Water Treatment Plant, Upgrade Storage, Upgrade Distribution System | 950 | $5,974,000 | H | $85,741,186 |
15590 | Steuben | VILLAGE OF SAVONA / SAVONA (V) | New system to serve area with private contaminated wells, consolidate public water supplies, eliminate public water supplies with past total coliform and nitrate detection., New Complete System (New System), System Consolidation | 974 | $5,991,262 | H | $91,732,448 |
15953 | Allegany | SCIO WATER DISTRICT / SCIO (T) | Upgrade existing treatment facility to include filtration for GWUDI springs, upgrade distribution system to correct inadequate distribution pressure violation., Upgrade Water Treatment Plant, Upgrade Ground Water Source, New Ground Water Source, Upgrade Distribution System | 1,039 | $1,463,280 | H | $93,195,728 |
17273 | Oswego | TOWN OF MEXICO AREA #1 / MEXICO (T) | New Ground Water Source, New Storage, New Distribution System | 1,400 | $8,480,000 | H | $101,675,728 |
16917 | Wayne | TOWN OF HURON WATER DISTRICT NO. 3 / HURON (T) | Extend Distribution System, System Consolidation | 210 | $931,500 | H | $102,607,228 |
17254 | Onondaga | SOUTHERN ONONDAGA CO. WATER SYSTEM / SPAFFORD (T) | Extend to serve private contaminated wells, consolidate public water supply, eliminate public water supply that has been determined to be GWUDI., Extend Distribution System, System Consolidation | 1,800 | $8,095,000 | H | $110,702,228 |
17373 | Oswego | (T) GRANBY WD#3 / GRANBY (T) | New Storage, New Pump Station, New Distribution System | 1,500 | $9,965,000 | H | $120,667,228 |
15940 | Jefferson | NATURAL BRIDGE WEST / WILNA (T) | Upgrade Ground Water Source, Upgrade Distribution System, System Consolidation | 72 | $875,000 | H | $121,542,228 |
17331 | Rensselaer | TOWN OF POESTENKILL WD #1 / POESTENKILL (T) | New Complete System (New System), New System Consolidation | 2,300 | $9,029,151 | H | $130,571,379 |
16991 | Chenango | OXFORD WATER DISTRICT #1 / OXFORD (T) | 50 | $122,500 | H | $130,693,879 | |
17225 | Oneida | HAMLET OF VIENNA WD / VIENNA (T) | New Surface Water Treatment Rule Compliance Facility, New Water District | 875 | $4,500,000 | H | $135,193,879 |
17388 | Essex | PORT KENT WD / CHESTERFIELD (T) | New Surface Water Treatment Rule Compliance Facility, New Ground Water Source, New Storage | 75 | $3,633,268 | H | $138,827,147 |
15586 | Cortland | MARATHON VILLAGE / MARATHON (V) | New Ground Water Source, New Transmission, Upgrade Distribution System | 1,107 | $930,000 | H | $139,757,147 |
17060 | Jefferson | TOWN OF CAPE VINCENT WD #4 / CAPE VINCENT (T) | New system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past total coliform detection. , Extend Distribution System, New System Consolidation, New Water District | 450 | $7,115,500 | H | $146,872,647 |
16289 | Steuben | CAMPBELL WATER SYSTEM / CAMPBELL (T) | New Ground Water Source, New Storage, New Distribution System | 425 | $3,100,000 | H | $149,972,647 |
16911 | Tioga | TOWN OF BARTON WATER DISTRICT / BARTON (T) | Extend to serve private contaminated wells, consolidate public water supplies, eliminate public water supplies with past coliform detections., Extend Distribution System | 1,500 | $984,400 | H | $150,957,047 |
17374 | Oswego | (T) NEWHAVEN WD#3 / NEW HAVEN (T) | New Pump Station, New Distribution System | 1,600 | $9,965,000 | H | $160,922,047 |
17372 | Oswego | (T) MEXICO WD#2 / MEXICO (T) | New Ground Water Source, New Storage, New Distribution System | 1,400 | $9,675,000 | H | $170,597,047 |
17192 | Cattaraugus | CENTRAL WATER DISTRICT / PERRYSBURG (T) | Upgrade Water Treatment Plant, Upgrade Ground Water Source, New Transmission, Extend Distribution System | 400 | $3,000,000 | H | $173,597,047 |
17201 | Jefferson | VILLAGE OF ELLISBURG / ELLISBURG (V) | Extend system to serve area with private contaminated wells, consolidate public water supply, eliminate public water supply with past total coliform detection. , Extend Distribution System, New System Consolidation | 269 | $2,992,700 | H | $176,589,747 |
16496 | Ulster | NAPANOCH WATER DISTRICT / WAWARSING (T) | New Ground Water Source, New Transmission | 200 | $7,649,100 | H | $184,238,847 |
17144 | Chemung | TOWN OF CHEMUNG WATER SYSTEM / CHEMUNG (T) | New Complete System (New System) | 280 | $5,651,000 | H | $189,889,847 |
17178 | Herkimer | MOHAWK VILLAGE / MOHAWK (V) | New Storage, Extend Distribution System, Upgrade Distribution System, New System Consolidation | 2,985 | $3,814,000 | H | $193,703,847 |
16510 | Schenectady | DELANSON VILLAGE WATER WORKS / DELANSON (V) | Improve inadequate system pressure, New Transmission, Upgrade Distribution System | 400 | $1,222,100 | H | $194,925,947 |
17140 | St.Lawrence | LOUISVILLE WATER DISTRICT #2 / LOUISVILLE (T) | 1,000 | $5,968,000 | H | $200,893,947 | |
16807 | Franklin | TUPPER LAKE (T) WD #17, LITTLE WOLF WD / TUPPER LAKE (T) | New system to serve area with private contaminated wells, consolidate public water supply. , New Complete System (New System) | 250 | $540,000 | H | $201,433,947 |
Total # Projects: 102 | Total Cost: $201,433,947 |